Road Paving Update

March 13, 2019

 

QH-ROAD UPDATE

 

Paving schedule for Queen’s Harbour will start on March 15, 2019.

 

Important information:

 

1. Turn off your sprinkler system before 5:00 AM the days your street is paved. Do not turn it back on until the day after your street is done.

 

2. Do not park on either side of the street during paving and edge milling.

 

3. Cones will be placed on the center lines of the street, and in the driveways on the side of the street that is being paved that day. Please park your car on a different street by 8:00 AM on the day(s) your street is being paved or plan to stay home for several hours. When the paving is dry enough to drive on, the cones will be removed.

 

4. If you drive in the wet paving, or allow your pets or children to walk on it, you will get black goo on your car or feet. It is hard to remove, and you will be responsible for cleaning. Neither the POA nor the Contractor are responsible for any material on your car, feet, or pets. 

 

5.Please do not turn your vehicle wheels while the vehicle is not in motion on the microseal surface. This will cause damage to the new microseal surface.

 

6. There will be flagmen at each intersection that is being worked on. Please follow their instructions. If you have a question, please ask them.

 

7. Instruction sheets will be placed on your front door on March 18th, and a representative of the contractor will knock on your door before they start work.

 

 

Schedule:

 

Friday, March 15

·    Grind the edges of all the curbs first at the below locations.

 

Monday, March 18

·    Finish grinding the edges of all the curbs first at the below locations.

 

Wednesday, March 20, Paving the following:

·    Moss Creek Drive

·    Charter Court

·    Windsor Harbor Drive

·    Queens Harbor Blvd-Harrington to South End

 

Thursday, March 21, Paving the following:

·    Moss Creek Drive

·    Charter Court

·    Windsor Harbor Drive

·    Queens Harbor Blvd-Harrington to South End

 

Friday, March 22, Paving the following:

·    Half of Harrington Park Drive

 

Monday, March 25, Paving the following:

·    Finish the other half Harrington Park Drive

 

Tuesday, March 26, Paving the following:

·    Pave parking area, close all windows and clean up.

 

Rain may delay the schedule. The streets that are being paved will be posted on the electronic reader board at the entrance, and reminders will be emailed the day before your street is being paved.

With your cooperation, we will have a smooth resurfacing.